Client
ENELPOWER
Owner
Royal Commission
Location
YANBU – Saudi Arabia
Scope of work
Design and Supply
Year of completion
2003
Status
Delivered
KEY STAFF
Project Director M. Rognoni
Project Manager P. Lucchi
Process Manager I. Izzo
Chief Designer L. Gaudio
Quality Controller M. R. Pascullo
PROCESS
Water to be treated Condensate at HP 33 bar
Total Capacity 780 m3/h
Number of lines 2 x 100%
Guaranteed TDS 0,1 ppm
Process Arrangement Mixed Bed Filters
Resins Type Rohm & Haas Amberjet 1200 Na + 4200 Cl
Regenerants Type Caustic Soda 40% / HCl 33%
Filters Material / Lining A 516 gr. 70. Internally rubber lined Thk 4 mm / Externally epoxy painted 250 µ
Notes:
Delivery scheduled in 9 months.