Client
ABB Sadelmi
Owner
Cinergy S.A.
Location
Azito – Ivory Coast
Scope of work
Design and Supply
Year of completion
1999
Status
In operation
KEY STAFF
Project Director M. Rognoni
Project Manager M. Rognoni
Process Manager L. Izzo
Chief Designer L. Izzo
Quality Controller A. Trezzi
PROCESS
Water to be treated Raw Water – Filtered Water – Waste water
Total Design Capacity Filtered Water 90 t/h – Demin Water 10 t/h
Number of lines 2×100% Raw Water – 2×100% Demin Water – 1×100% Waste Water
Guaranteed TDS (*) 0,01 ppm
Process Arrangement Raw Water: Dual Media Filters – Demin. Water: Mixed Bed Filters
Resins Type (*) Rohm & Haas Amberjet 1200 H – 4200 Cl
Regeneration System (*) Counter Flow
Regenerants Type (*) H2SO4 98% + NaOH 40%
Filters Material / Lining SA 516 Gr. 60 DMF Intern. epoxy painted – MBF Intern. rubber lined thk 3 mm
Notes:
Plant delivered in 6-7 months in accordance with contractual schedule.
Site services performed for supervision and commissioning.