11-249 CADAFE Venezuela

Client
CADAFE
Owner
CADAFE
Location
Planta Centro—Venezuela
Scope of work
Turn-key
Year of completion
2005
Status
In progress

KEY STAFF

Project Director M. Rognoni
Project Manager P. Lucchi
Process Manager A. Trezzi
Chief Designer A. Trezzi
Quality Controller D. Quaranta

PROCESS

Water to be treated Sea water
Total Design Capacity 5,000 t/d
Number of units 2×50%
Guaranteed TDS 5 ppm
Process Arrangement TVC (Thermo Vapor Compr.) total 6 effects
Tubes material Al 5052
Shell material C.S. Epoxy Painted
Tubes fixing Rubber grommets
Top Brine Temperature 69°C

Download files connected with the Project

For any further information whatsoever contact: swsinfo@swsonweb.com