Client
COMMISSIONING
Owner
ELETTRA (LUCCHINI)
Location
Piombino (Italy)
Scope of work
Design and Supply
Year of completion
2001
Status
Delivered
KEY STAFF
Project Director M. Rognoni
Project Manager P. Lucchi
Process Manager A. Trezzi
Chief Designer L. Gaudio
Quality Controller M. R. Pascullo
PROCESS
Water to be treated Condensate from steam turbine condenser + make up
Total Capacity 150 m3/h
Number of units 1
Guaranteed O2 content 0,005 ppm
Process Arrangement Spray and Trays thermal deaerator
Design pressure 4 bar abs/Full Vacuum
Design temperature 184°C
Materials Hold up tank:SA516 Gr. 65 – Deaerating tower internals: AISI 316 L
Notes:
Equipment delivered in 6 months in accordance with contractual schedule.
Design of spray valves and splashing trays by SWS.
ISPESL approved and stamped.
Download files connected with the Project
For any further information whatsoever contact: swsinfo@swsonweb.com