AE-085Deg

Client
Technip-Bechtel J.V.
Owner
ADNOC (OGD 2 Project)
Location
MYKONOS (GREECE)
Scope of work
Design and Supply
Year of completion
1999
Status
In operation

KEY STAFF

Project Director M. Rognoni
Project Manager M. Rognoni
Process Manager B. Granata
Chief Designer B. Granata
Quality Controller A. Trezzi

PROCESS

Water to be treated Condensate from steam turbine condenser
Total Capacity 520 m3/h each unit
Number of unit 2 x 100%
Guaranteed O2 content 0,007 ppm
Process Arrangement Spray and Trays thermal deaerator
Design pressure 3,5 barg / Full Vacuum
Design temperature 173 °C
Materials Hold up tank: SA516Gr.65 – Deaerating tower: AISI 316L

Notes:

Equipment delivered in 6 months in accordance with contractual schedule.
Spray valves and splashing trays by SWS