Client
EUROPOWER
Owner
MALPENSA ENERGIA
Location
Italy – Linate Airport
Scope of work
Design and Supply
Year of completion
2006
Status
Delivered
KEY STAFF
Project Director P. Lucchi
Project Manager F. Volpe
Process Manager P. Freddo
Chief Designer P. Freddo
Quality Controller G. Ardizzola
PROCESS
Water to be treated Oily drains
Total Design Capacity 5 m3/h
Number of units 1
Guarantee 5 ppm of residual oil
Process Deoiling Air flotation
Process Neutralization N. A.
Pumps Submergible pumps
Location Outdoor
Download files connected with the Project