41-393 Chivasso R

Client
ENELPOWER
Owner
EDISON
Location
CHIVASSO – Italy
Scope of work
Turn-key
Year of completion
2004
Status
Completed

KEY STAFF

Project Director P. Lucchi
Project Manager F. Volpe
Process Manager M. Galante
Chief Designer F. Volpe
Quality Controller D. Quaranta

PROCESS

Water to be treated Condensate at HP 30 bar
Total Capacity One line x 425 m³/h + one line x 850 m3/h
Number of lines 2
Guaranteed SS < 2 μ
Process Arrangement Cartridge Filter (backwashable polypropylene)
Cartridges Arrangement Each 2” x 60”, made of P.P. (number 109 and 210)
Backwash By air impulse, controlled by PLC
Filters Material / Lining A 516 gr. 70. Internally rubber lined Thk 4 mm / Externally epoxy painted 250 µ

NOTES

– Innovative process scheme, basic designed by ENEL and engineered by SWS
– Plant entirely skidded and wired at site (filters Ø 1500 and 2100 delivered
separately)
– Precoat system installed