21-743 KHURSANIYA

Client
ARAMCO by SNAMPROGETTI
Owner
ARAMCO
Location
Saudi Arabia
Scope of work
Design and Supply
Year of completion
2005
Status
Delivered

KEY STAFF

Project Director P. Lucchi
Project Manager A. Spada
Process Manager D. Bonicelli
Chief Designer D. Bonicelli
Quality Controller G. Ardizzola

PROCESS

Water to be treated Condensate
Total Capacity 2,680 t/h
Number of units 2×50%
Guaranteed O2 content 0,005 ppm
Process Arrangement Spray and Trays deaerator
Design pressure 4.5 bar abs/Full Vacuum
Design temperature 197 °C
Materials
Deaerating tower : SS316L
Storage Tank: SA516Gr.70
Internals SS316L

Notes:

Design of spray valves and trays by SWS. Trays mod. WTA for enhanced water flow.
Tower arranged horizontally connected to the tank with 1 downcomer + 1 balance + 2 saddles.
Fabrication made in the workshop of Hidada.

Download files connected with the Project

21-743 KHURSANIYA
523.pdf (94 KB)

For any further information whatsoever contact: swsinfo@swsonweb.com