21-468 Dolphin Qatar

Client
J.G.C.
Owner
Dolphin
Location
Qatar
Scope of work
Design and Supply
Year of completion
2005
Status
Delivered

KEY STAFF

Project Director M. Rognoni
Project Manager P. Lucchi
Process Manager D. Bonicelli
Chief Designer D. Bonicelli
Quality Controller D. Quaranta

PROCESS

Water to be treated Condensate + Demi
Total Capacity 1382 t/h each unit
Number of units 2
Guaranteed O2 content 0,010 ppm
Process Arrangement Spray and Trays thermal vacuum deaerator
Design pressure 3.5 bar abs/Full Vacuum
Design temperature 270 °C
Materials
Deaerating tower : S.S. 316 L
Internals AISI 316 L

Notes:

Design of spray valves and trays by SWS. Trays mod. WTA for enhanced water flow.
Tower arranged horizontally connected to the tank with 1 downcomer + 4 nozzles.

Download files connected with the Project

21-468 Dolphin Qatar
521.pdf (111 KB)

For any further information whatsoever contact: swsinfo@swsonweb.com